Services

Organization Chart

Document Inquiry

Licence

Our Management

Information

Procedue


N Garden Sheds Enterprise
169A, Jalan Seri Impian 1,
Taman Impian Emas,
Skudai, 81300 Johor.
07-5591325/5578995
07-5579016
n_garden_sheds

Construction Sector

CRITERIA/ELIGIBILITY FOR EMPLOYMENT OF FOREIGN WORKERS FOR THE CONSTRUCTION SECTOR

1. Basic Formula Of Calculation

a. Based On Project Value (material + labour)

Project Value (RM)

x

15%

x

1 month

Duration (month)

 

Worker Salary

b. Based On Labour Cost

Project Value (RM)

x

70%

x

1 month

Duration (month)

 

Worker Salary


2.   Estimation Of Workers Requirement

 

Type of Construction Project

Factor Of Gross CL*

Requirement Per RM 1.0 Mil

Project Value

1.

Low Rise Building (4 storeys and less)

150 x PV
  D

2.

High Rise Building (above 4 storeys)

150 x PV
  D

3.

Infrastructure Works

Road/Highway

Bridges

Piping Works (>1350 mm dia.)

Retaining Walls

Sewerage

Land Reclamation

Overhead Transmission Power Line

Underground Cable

100 x PV
  D

4.

Building Services

Electrical Wiring

Fire Fighting Installation

Telecommunication Cabling

80 x PV
 D

5.

Landscape

80 x PV
 D

Note:
CL ĘC Construction Labour
D ĘC Duration
PV ĘC Project Value

3. Estimation On Construction Labour Requipment

GCLR ĘC TACL = ECLR

Where

GCLR = Gross Construction Labour Requirement
TACL= Total Available Construction Labour (Local + Foreign)
ECLR= Estimated Construction Labour Requirement

ECLR will be the guided figure to recommend di Jawatankuasa Teknikal JKT at Kementerian Hal Ehwal Dalam Negeri KHEDN after taking into consideration other government policies which formulated by Kementerian Sumber Manusia

4. Verification Of Information

Whenever any uncertainties arise, then verification of the information will be made through as follows:

4.1. Phone call
4.2. Interview
4.3.  Visit to the site or premise

5. Blacklisted The Contractor

In any event where the contractor is found to provide false information, then it shall be blacklisted. Whereby any future applications from the respective contractor will not be considered by the technical committee.